ST HILLERS CONSTRUCTION PTY LTD, ST HILLIERS CONSTRUCTION PTY LTD, ST HILLIERS CONTRACTING PTY LTD, STHILLIERS CONTRACTING PTY LIMITED
Open 36 contracts, 70.59%, Prequalified 8 contracts, 15.69%, limited 7 contracts, 13.73%,
Contracts
Contract Notice Number |
Contract Description |
Total Contract Value |
Agency |
Contract Start Date |
Supplier |
197106-A13 |
Provision of fitout for Edmund Barton Building |
$143,004,219.89 | Australian Federal Police |
2009-05-22 |
St Hilliers Contracting Limited |
466344 |
Redevelopment of Greenbank Training Area |
$103,174,582.50 | Department of Defence |
2012-02-08 |
ST HILLIERS CONSTRUCTION PTY LTD |
20477-A1 |
Capital Expenditure - Buildings (GAPS ID: 1646283) |
$37,120,045.00 | Department of Finance and Administration |
2006-09-25 |
ST HILLIERS CONTRACTING PTY LTD |
90014-A1 |
Fitout Services, Caroline Chisholm Centre, Tuggeranong, ACT |
$34,373,566.37 | Centrelink |
2007-08-23 |
St Hilliers Contracting Pty Ltd |
466267-A2 |
Variation to the contract for works associated with theEnhanced Land Force Stage 2C - Wide Bay Training Area Project |
$31,041,475.30 | Department of Defence |
2011-11-23 |
ST HILLIERS CONSTRUCTION PTY LTD |
20497-A1 |
Capital Expenditure - Buildings (GAPS ID: 1629184) |
$24,050,387.90 | Department of Finance and Administration |
2006-09-25 |
ST HILLIERS CONTRACTING PTY LTD |
20482 |
Capital Expenditure - Buildings (GAPS ID: 1646285) |
$18,127,041.90 | Department of Finance and Administration |
2006-09-25 |
ST HILLIERS CONTRACTING PTY LTD |
365029 |
wide bay training area |
$17,844,744.50 | Department of Defence |
2010-12-07 |
ST HILLIERS CONSTRUCTION PTY LTD |
352967 |
ELF STAGE 2 WATSONIA TECHNICAL TRAINING WING (TTW) |
$15,526,363.60 | Department of Defence |
2010-11-29 |
ST HILLIERS CONSTRUCTION PTY LTD |
20505 |
Capital Expenditure - Buildings (GAPS ID: 1629185) |
$13,069,657.70 | Department of Finance and Administration |
2006-09-25 |
ST HILLIERS CONTRACTING PTY LTD |
20490 |
Capital Expenditure - Buildings (GAPS ID: 1646286) |
$10,180,643.00 | Department of Finance and Administration |
2006-09-25 |
ST HILLIERS CONTRACTING PTY LTD |
368403 |
Building fitout |
$9,373,741.30 | Attorney-General's Department |
2011-02-02 |
St Hilliers Construction Pty Ltd |
460831 |
Head contractor for the construction of the LAND12 facilities at Bandiana |
$8,656,318.00 | Department of Defence |
2012-01-16 |
ST HILLIERS CONSTRUCTION PTY LTD |
340832 |
PROVISION OF A CONSTRUCTION CONTRACTOR FOR THE NAISDA REFURBISHMENT PROJECT |
$5,335,280.50 | Department of the Environment Water Heritage and the Arts |
2010-08-04 |
St Hilliers Construction Pty Ltd |
416435 |
wide bay training area |
$5,269,149.54 | Department of Defence |
2011-06-06 |
ST HILLIERS CONSTRUCTION PTY LTD |
1083942 |
Head Contract for the construction of Greenbank Training Area |
$3,979,135.05 | Department of Defence |
2012-10-18 |
ST HILLIERS CONSTRUCTION PTY LTD |
421959 |
NAISDA Dance College Capital Upgrade |
$3,780,670.23 | Department of the Prime Minister and Cabinet |
2010-08-04 |
ST HILLERS CONSTRUCTION PTY LTD |
71191 |
Capital + Expense costs for NSW Fitout 341 George Street Syd |
$3,362,845.20 | Department of Industry, Innovation and Science |
2008-02-01 |
ST HILLIERS CONTRACTING PTY LTD |
435362 |
wide bay training area |
$3,347,098.14 | Department of Defence |
2011-08-22 |
ST HILLIERS CONSTRUCTION PTY LTD |
20484 |
Capital Expenditure - Buildings (GAPS ID: 1646284) |
$2,889,014.70 | Department of Finance and Administration |
2006-09-25 |
ST HILLIERS CONTRACTING PTY LTD |
2220971 |
wide bay training area |
$2,361,312.82 | Department of Defence |
2011-10-06 |
ST HILLIERS CONSTRUCTION PTY LTD |
61459 |
Capital Expenditure - Buildings |
$2,317,502.00 | Department of Finance |
2008-02-12 |
ST HILLIERS CONTRACTING PTY LTD |
481090 |
Building Fitout |
$1,901,796.60 | Attorney-General's Department |
2010-10-07 |
St Hilliers Construction Pty Ltd |
416716 |
Road Maintenance |
$1,608,750.00 | Department of Defence |
2011-07-19 |
ST HILLIERS CONSTRUCTION PTY LTD |
95217 |
Capital Expenditure - Buildings |
$1,458,052.60 | Department of Finance |
2008-06-26 |
ST HILLIERS CONTRACTING PTY LTD |
835941 |
Head Contract for the construction of Enhanced Land Force Stage 2C-Greenbank Training Area |
$1,265,046.75 | Department of Defence |
2012-04-16 |
ST HILLIERS CONSTRUCTION PTY LTD |
25114 |
Capital Expenditure - Buildings |
$1,107,011.95 | Department of Finance and Administration |
2005-09-29 |
ST HILLIERS CONTRACTING PTY LTD |
1676871 |
Head contractor for facilities construction |
$991,603.65 | Department of Defence |
2013-04-03 |
ST HILLIERS CONSTRUCTION PTY LTD |
251286 |
Mint Managing contractor |
$872,852.30 | Department of Finance and Deregulation |
2009-05-28 |
ST HILLIERS CONTRACTING PTY LTD |
560122 |
Head Contract for Technical Training Wing |
$788,099.25 | Department of Defence |
2012-05-22 |
ST HILLIERS CONSTRUCTION PTY LTD |
251284 |
Mint Managing contractor |
$607,566.37 | Department of Finance and Deregulation |
2009-05-28 |
ST HILLIERS CONTRACTING PTY LTD |
181433 |
fitout |
$505,752.50 | Royal Australian Mint |
2009-04-22 |
STHILLIERS CONTRACTING PTY LIMITED |
491741 |
ELF STAGE 2 WATSONIA TECHNICAL TRAINING WING (TTW) |
$452,483.64 | Department of Defence |
2012-05-03 |
ST HILLIERS CONSTRUCTION PTY LTD |
796091 |
Head Contract for Technical Training Wing (Enhanced Land Force Phase 2C) Defence Force |
$440,989.76 | Department of Defence |
2012-08-01 |
ST HILLIERS CONSTRUCTION PTY LTD |
462590 |
ELF STAGE 2 WATSONIA TECHNICAL TRAINING WING (TTW) |
$229,130.04 | Department of Defence |
2012-02-06 |
ST HILLIERS CONSTRUCTION PTY LTD |
358364 |
Building Fit Out |
$208,302.60 | Attorney-General's Department |
2010-12-17 |
St Hilliers Construction Pty Ltd |
453778 |
ELF STAGE 2 WATSONIA TECHNICAL TRAINING WING (TTW) |
$146,737.56 | Department of Defence |
2011-02-01 |
ST HILLIERS CONSTRUCTION PTY LTD |
927501 |
Head Contract for Technical Training Wing (Enhanced Land Force Phase 2C) Defence Force |
$139,951.08 | Department of Defence |
2012-09-04 |
ST HILLIERS CONSTRUCTION PTY LTD |
480302 |
ELF STAGE 2 WATSONIA TECHNICAL TRAINING WING (TTW) |
$132,835.82 | Department of Defence |
2012-04-16 |
ST HILLIERS CONSTRUCTION PTY LTD |
26510 |
REFURBISH PARQUETRY FLOORING |
$107,982.06 | Royal Australian Mint |
2007-08-13 |
STHILLIERS CONTRACTING PTY LIMITED |
653881 |
Head Contract for Technical Training Wing (Enhanced Land Force Phase 2C) Defence Force |
$96,978.36 | Department of Defence |
2012-06-20 |
ST HILLIERS CONSTRUCTION PTY LTD |
1334121 |
Head Contract for Technical Training Wing |
$86,315.86 | Department of Defence |
2013-04-15 |
ST HILLIERS CONSTRUCTION PTY LTD |
990991 |
P10093 CCC Fitout Trades |
$78,344.64 | Attorney-General's Department |
2012-10-19 |
St Hilliers Construction Pty Ltd |
991001 |
CCC Fitout Prelims |
$63,228.54 | Attorney-General's Department |
2012-10-19 |
St Hilliers Construction Pty Ltd |
1216812 |
Head contractor for the construction of the Land 121 facilities at Gaza Ridge Barracks |
$47,793.51 | Department of Defence |
2013-02-21 |
ST HILLIERS CONSTRUCTION PTY LTD |
1026631 |
Head Contract for Land Engeering Agency Relocation-Monegeetta |
$36,526.56 | Department of Defence |
2012-10-23 |
ST HILLIERS CONSTRUCTION PTY LTD |
1612341 |
Construction Work on Army Facilities |
$32,701.16 | Department of Defence |
2013-07-18 |
ST HILLIERS CONSTRUCTION PTY LTD |
476135 |
Head contractor for the construction of the LAND12 facilities |
$26,831.28 | Department of Defence |
2012-03-27 |
ST HILLIERS CONSTRUCTION PTY LTD |
1731281 |
Construction Work on Army Facilities |
$25,730.58 | Department of Defence |
2013-07-31 |
ST HILLIERS CONSTRUCTION PTY LTD |
1188631 |
Head contractor for the construction of the Land 121 facilities at Gaza Ridge Barracks North |
$19,201.65 | Department of Defence |
2012-05-16 |
ST HILLIERS CONSTRUCTION PTY LTD |
1460351 |
Construction Work on Army Facilities |
$17,008.96 | Department of Defence |
2013-06-05 |
ST HILLIERS CONSTRUCTION PTY LTD |